The Church That Cares For Your Soul

Church Building Project

Update – September 12th, 2020

Over the past 2 days, 10 concrete trucks and about 20 hours of work went into pouring the main concrete pad as well as the entrances. (See time-lapse below) – Lord willing, the framers should begin in the next week or so.

Update – August 29th, 2020

After finishing the plumbing and insulation, we moved on to grading the stone and then laying plastic and metal griding to prepare for pouring the concrete. Most of the prep steps are complete an we should be pouring concrete in the next couple weeks.

Update – August 20th, 2020

The foundation is in and we are focused on completing the plumbing that will go under the concrete pad. Next Step will be to grade gravel over the the whole thing to prepare for pouring the concrete pad.

Update – August 8th, 2020

Despite another 6 inches of rain the night before, we were still able to get the block foundation for the main building built. Next Steps are to finish the blocks around the doors, setting up the plumbing that will go under the concrete, and pouring the main pad.

Update – August 5th, 2020

Despite a last minute Tropical Storm hitting the property, we were able to get the footers poured today. We showed up at the property around 6AM and needed to redig the footers because all the rain had caused them to collapse in. We then had to remove and replace the rebar. God truly blessed this because we were able to get all this work done and inspected by the time that the Concrete trucks showed up at 11AM.

Update – August 1st, 2020

We are now starting to see progress. The foundation was fully laid today and the rebar is set for the footers to be poured next week.

Update – July 28th, 2020

A little more work being done here today. Almost done with building up the ground and prepping for digging the footers this Saturday.

Update – July 25th, 2020

We are plugging on with the land development. A good portion of the new driveway has been dug out and we are building up the lower end of the property with dirt from the driveway and some fill dirt that was trucked in over the week.

Update – July 18th, 2020

Surveying has now been completed and we are working on the Land Development Steps. The retention pond has been dug, seeded and fenced in and is being scheduled for inspection. The next Land Development task is to flatten the area where the Parking Lot and Building will be. This will require several truck loads of Fill Dirt raise the low part of the property.

Group of Teens working to install Filter Sock in the Retention Pond at the new property.

Update – July 11th, 2020

We have finished cutting down trees and all of the stumps have been removed. The next step is Land Development and we are starting with putting in the Retention Pond. The Surveyor is also scheduled to start next week.

Update – June 30th, 2020

Most of the Trees have been cut down and ground up over the course of several working days in the past 2 weeks.

The Truck shown in the Video was donated Courtesy of Weaver Mulch

Update – June 15th, 2020

Final Building Plans have been approved and we are cleared to start cutting down trees and beginning Land Development.

Update – January 2020

Land Development plans have been approved and we are awaiting Final Approval of Building Plans to begin construction.

Orignal Post – September 2015

We have officially begun a church building project.  We had our first dedication church service at the new property donated to us by BB&T Bank (Formerly Susquehanna Bank).  The property is located at 682 Gap Newport Pike (State Route 41) in Atglen, Pennsylvania.  The church service

Dedication Church Service
Dedication Church Service

opened with prayer, thanking the Lord for graciously giving us the property and asking his blessing on the property that it would be used for his glory and honor to reach the lost and be a tool He could use.  We asked the Lord that he would send revival to Chester County and we could see souls saved.  Pastor Keenan is praying for nine new families.

After prayer we sang some hymns including “To God Be The Glory.”  Pastor Keenan preached a short message from Nehemiah about using a few to rebuild the wall.  We are few but God can show himself mighty.

After the service everyone milled about the property and discussed about where we would like to build.  The kids really enjoyed the woods and having a place to roam.  The Lord has truly been good to us.

Kids Playing at New Property
Kids Playing at New Property

0 Comments

Leave a Reply